Ramadan Announced - First Taraweeh 17th Feb

Jummah Times Change to 12:45 / 1:15

Masjid Al-Hikmah
Masjid Al-Hikmah
22 February 2026 0
Fajr
5:39
Zuhr
13:00
Asr
16:15
Magh
17:31
Isha
19:30

Building for the Future

Construction Progress

Follow the rebuild of Masjid Al-Hikmah — from groundworks to grand opening.

Milestones Complete

4 / 13

31% of project complete

Currently Underway

Phase 1 Open for Use

Active

Next Milestone

Phase 2 Commencement

April 2026

Grand Opening

Late January 2027

Grand Opening

Commencement of works — March 2025
Complete

March 2025

Commencement of Works

New contractors appointed and plans revised.

Corrective works — September 2025
Complete

September 2025

Corrective Works Complete

Corrective works from previous contractors and teams.

First fix complete — October 2025
Complete

October 2025

First Fix Complete

Plumbing, Electrical, Plant Room, Whudu Area & W/C's

Second fix complete — February 2026
Complete

February 2026

Second Fix Complete

Tiling, Fixtures & Fittings, Doors, Windows, Carpets

Phase 1 open for use — March 2026
In Progress

March 2026

Phase 1 Open for Use

Building to be used for Madrassah.

Upcoming

April 2026

Phase 2 Commencement

Finalisation of Phase 2 Plans.

Upcoming

May 2026

Deconstruction

The main building will be completely deconstructed, leaving only the front facade remaining.

Upcoming

July 2026

Groundworks & Foundations

Excavation, concrete foundations and drainage installed.

Upcoming

August 2026

Structural Works

Steel frame and masonry walls erected, roof structure completed.

Upcoming

November 2026

First Fix

Electrical, plumbing and heating services run through the structure.

Upcoming

December 2026

Second Fix

Sockets, switches, sanitaryware, doors and plastering completed.

Upcoming

January 2027

Fit Out & Finishing

Prayer hall carpets, mihrab, minbar, sound system, lighting and final finishes installed.

Upcoming

Late January 2027

Grand Opening

Masjid Al-Hikmah opens its doors — just in time for Ramadan 2027.